CDC collaborates on fiber optic project.
What have we implemented?
CDC participates in fiber optic project at our northern neighbors in the municipality of Westerwolde and the municipality of Stadskanaal.
For this project, the PoP stations (Point of Presence) or concrete cabins were supplied by CDC – Cabines de Ciney and custom equipped and transported by Tecnolimit System Integrations. Thanks in part to the many color possibilities of the concrete, these PoP stations blend in well with any urban environment.

On site, the ground has already been excavated and the crane is ready to place the PoP station in the construction pit. Next, the PoP station can be connected and is the main distribution station from which the fiber optic cables enter the residential areas. Within the foreseeable future, this will allow many households to use the high-speed fiber optic Internet connection.
Technical specifications
The cabin has an aluminum door with dimensions 920x2045mm.
The door is right-handed and equipped with an Assa Abloy motor lock.
The interior and exterior handles are of the Dorma TS83 type.
The cab has a RAL 7035 color and is equipped with a double-sloped roof with a 1% slope. The roof is constructed with Hauff technique HSI 90: 15 and HEA IM12 profiles.
The basement has a height of 650mm. The total weight is 22,500 kg, of which 18,700 kg is for the cab and 3,800 kg for the roof.
The top of the roof has a gray epoxy coating. For optimum sealing, a rubber seal was placed between the roof and the cabin. An epoxy coating was applied in the basement.